Orange County FL Inspection Type Codes — What Each Inspection Means
Orange County uses numerical inspection codes for building, electrical, mechanical, plumbing and gas permits. This guide translates the codes into plain English, explains when each inspection is typically requested, and gives practical tips for avoiding covered-work and permit-closeout problems.
Building Inspection Codes
Building inspections generally follow the construction sequence from site work and foundations through framing, insulation, roofing and final occupancy/permit closeout. The exact inspections shown on your permit control.
| Code | Inspection | When it is commonly needed | Practical tip | Engineer-letter relevance |
|---|---|---|---|---|
| 100 | Site | Early site inspection where setbacks, layout, access, grading or other site conditions must be checked before construction advances. | Have permit plans and site layout available; verify property lines/setbacks before irreversible work. | Usually low |
| 110 | Footing / Foundation | Before concrete is placed, while excavations, reinforcing steel, forms and bearing conditions are visible. | Do not pour until the required inspection is approved. If already poured, documentation and County direction become critical. | Common missed-inspection issue |
| 115 | Stemwall | For masonry or concrete stemwall construction, generally before the work is concealed or backfilled. | Keep reinforcing, cells, dowels and connections visible for inspection. | Possible |
| 120 | Slab | Before slab placement, typically after base preparation, vapor barrier, reinforcement and embedded items are ready. | Photograph reinforcement, vapor barrier, sleeves and dimensions before the pour. | Common |
| 121 | Sidewalk & Driveway | For permitted flatwork, driveway approaches, accessibility-related work or site improvements. | Confirm slope, thickness, reinforcement and right-of-way requirements before placement. | Case specific |
| 130 | Footing / Slab (Monolithic) | For monolithic slab-on-grade foundations where the thickened edge/footing and slab are poured together. | This is a high-value inspection to photograph thoroughly before concrete. | Common |
| 135 | Flood Plain Certification | When a project is in a regulated flood hazard area and elevation/floodplain compliance must be documented. | Coordinate survey/elevation documentation early; flood approvals can hold up final closeout. | Possible specialized certification |
| 150 | Lintel / Tie-Beam | For masonry wall lintels, reinforced tie beams and related reinforcing before grout/concrete conceals the steel. | Keep rebar, laps, dowels and cells visible. | Common covered-work issue |
| 170 | Down Pour | Generally used for a concrete/grout placement stage associated with reinforced masonry or other permitted structural work. | Verify what the permit card specifically requires before placement; terminology can be project-specific. | Case specific |
| 180 | Tilt Panel | For tilt-up concrete panel construction and related structural installation. | Commercial/specialty inspection; coordinate erection and connection documentation. | Specialty |
| 188 | Window Installation | After windows/doors are installed while attachment, flashing and perimeter conditions remain verifiable. | Keep product approvals, installation instructions and anchor information on site. | Common ATF topic |
| 189 | Exterior Framing | For exterior wall/framing work prior to concealment by finishes. | Do not cover sheathing, connectors or framing modifications before approval. | Common |
| 190 | Framing | After structural framing is substantially complete and before insulation/drywall conceals members and connections. | Have truss engineering, headers, connectors and approved revisions available. | Very common |
| 191 | Fire Rated Assembly | Where rated walls, floors, ceilings or penetrations must be verified before concealment. | Use listed assemblies and keep labels/details available. | Specialty |
| 192 | Above Ceiling / Fire Penetrations | Before suspended ceilings close access to rated penetrations, firestopping and above-ceiling systems. | Do not install final ceiling tiles before required inspection. | Specialty |
| 210 | Insulation | After insulation is installed but before drywall or other finishes conceal it. | Make sure R-values, installation depth and coverage are visible. | Common missed inspection |
| 211 | Lath | For stucco/plaster lath, weather-resistive barrier and related attachments before finish coats. | Photograph WRB laps, flashing and fastener spacing before stucco. | Common exterior ATF topic |
| 270 | Landscaping Final (Zoning) | Near project closeout where required landscaping/zoning conditions must be verified. | Check approved landscape/zoning plans, not only building plans. | Usually not an engineer letter |
| 279 | Roof Flashing (Other) | For flashing details that must be seen before roofing/finish work conceals them. | Photograph underlayment, flashings and penetrations in-progress. | Possible roof affidavit issue |
| 280 | Roof Final (Re-Roof & New Roof) | At completion of new roofing or reroofing work. | Keep product approvals, permit documents and any required in-progress photos available. | Common permit-closeout issue |
| 281 | Re-Roof / In-Progress | During reroofing while underlayment, attachment or other required concealed components are still visible. | Do not finish the roof before this inspection if it is listed on the permit. | Very common missed inspection |
| 290 | Final | At project completion after required trade and prerequisite inspections are approved. | Resolve outstanding corrections and paperwork before scheduling. | Closeout related |
| 300 | Use Permit | For projects requiring a use permit inspection before occupancy/use approval. | Confirm all use-permit conditions and related fire requirements. | Usually administrative/field |
| 310 | Demolition | For permitted demolition work and site closeout. | Verify utilities, debris removal and site conditions required by the permit. | Usually low |
| 360 | Mobile Home Tie Down | For manufactured/mobile home anchorage, tie-down and stabilization systems. | Keep foundation/tie-down system information and visible anchors available. | Potential engineering certification |
| 370 | Tank Pressure & Anchorage | For permitted tanks where pressure and anchorage requirements must be verified. | Coordinate testing records and anchorage details before inspection. | Specialty |
| 390 | Tank Gasoline Piping Pressure | For gasoline tank/piping systems requiring pressure testing. | Testing typically needs to be witnessed/documented; do not bury or conceal piping prematurely. | Licensed trade/specialty |
| 590 | Fire Final | Final fire/life-safety inspection where required by permit or occupancy. | Coordinate separately with applicable fire authority requirements. | Usually not replaced by PE letter |
Electrical Inspection Codes
| Code | Inspection | When it is commonly needed | Practical tip | Engineer-letter relevance |
|---|---|---|---|---|
| 400 | Temporary Construction Service | For temporary power serving an active construction site. | Coordinate utility/service requirements with the electrical contractor. | Usually trade inspection |
| 405 | TUG | Temporary underground/service stage as identified by the permit and electrical utility coordination. | Confirm the County/utility sequence before energization. | Usually trade inspection |
| 410 | Underground | Before underground electrical conduit/conductors are covered or backfilled. | Leave trench, conduit depth and routing visible. | Common covered-work issue |
| 415 | Deck | Electrical inspection associated with deck/pool/deck-area wiring as required by the permit. | Verify bonding/GFCI and wiring scope with the electrical contractor. | Case specific |
| 420 | Rough-In | After wiring, boxes and equipment rough-in are installed but before walls/ceilings are closed. | Do not drywall before rough-in approval. | Very common missed inspection |
| 425 | Footer Bonding | For concrete-encased electrode/bonding work before concrete placement. | This becomes inaccessible after the pour; inspect before concrete. | High concealment risk |
| 480 | TUG Changeover | When temporary utility/service configuration is transitioned as permitted. | Coordinate County approval and utility scheduling. | Usually trade/utility |
| 490 | Final | When electrical work is complete, devices/covers are installed and the system is ready for final approval. | Correct panel labeling, GFCI/AFCI, covers and equipment issues before scheduling. | Closeout related |
| 500 | Meter Reset | Where service work requires authorization to reset/reconnect the meter. | Coordinate contractor, County and utility timing. | Usually trade/utility |
| 510 | Use Permit | Electrical component of a use/occupancy permit process where required. | Confirm exact prerequisites in Fast Track. | Usually low |
| 520 | Change of Service | For electrical service replacements/upgrades or changes in service equipment. | Have approved service size and equipment details ready. | Case specific |
Mechanical Inspection Codes
| Code | Inspection | When it is commonly needed | Practical tip | Engineer-letter relevance |
|---|---|---|---|---|
| 600 | Underground | For mechanical piping/duct or related work installed below grade before cover. | Keep routing and connections exposed. | Possible missed inspection |
| 610 | Rough-In | For ductwork, lines, equipment rough-in and related mechanical work before ceilings/walls conceal it. | Do not close ceilings/walls before approval. | Very common |
| 690 | Final | When HVAC/mechanical installation is complete and operational. | Have model numbers, disconnects, condensate disposal and required clearances ready for review. | Common permit closeout |
| 700 | Pipe Pressure | When mechanical piping requires a pressure test before concealment/operation. | Schedule while the test can be observed and documented. | Licensed trade/testing |
| 710 | Pipe Insulation | After required piping insulation is installed and before concealment where applicable. | Keep thickness and continuity visible. | Case specific |
| 720 | Hood / Ventilation | For kitchen/commercial hood or ventilation systems. | Keep manufacturer data, duct details and fire-system coordination available. | Specialty |
| 730 | Fire Damper | For fire/smoke dampers in rated assemblies before access is restricted. | Preserve access, labels and listed installation details. | Specialty |
| 740 | Fire Stopping | For firestopping associated with mechanical penetrations in rated assemblies. | Use listed systems and keep product/assembly information available. | Specialty |
| 750 | Refrigeration | For refrigeration systems and related mechanical equipment when separately required. | Coordinate pressure testing, equipment data and manufacturer requirements. | Specialty |
Plumbing Inspection Codes
| Code | Inspection | When it is commonly needed | Practical tip | Engineer-letter relevance |
|---|---|---|---|---|
| 800 | Sewer | For building sewer installation or repair before concealment/backfill as required. | Keep pipe slope, cleanouts and connections visible. | Possible covered-work issue |
| 810 | Underground | For below-slab/below-grade plumbing before cover or concrete. | Photograph piping layout and leave test/setup accessible. | Very common missed inspection |
| 820 | Irrigation | For permitted irrigation work where required. | Confirm backflow and zoning requirements applicable to the permit. | Usually low |
| 830 | Rough-In | After supply, waste and vent piping are roughed in but before walls/floors conceal them. | Do not close walls until rough-in approval; keep pressure/test setup available if required. | Very common |
| 880 | Solar | For plumbing-related solar systems where the permit requires this inspection. | Keep piping, valves and equipment data accessible. | Specialty |
| 890 | Final | When plumbing fixtures, connections and permitted work are complete. | Check leaks, fixture operation, cleanouts and final accessibility before scheduling. | Closeout related |
Gas Inspection Codes
| Code | Inspection | When it is commonly needed | Practical tip | Engineer-letter relevance |
|---|---|---|---|---|
| 650 | Rough-In | After gas piping is installed and pressure-test conditions are ready, before concealment. | Do not cover piping before required test/inspection. Keep licensed gas contractor documentation. | Possible, but trade testing is critical |
| 660 | Final | At completion of gas system/appliance installation after required rough-in approvals. | Verify appliance connections, shutoffs, venting/combustion-air requirements and leak-free operation. | Case specific |
What if the Orange County inspection was missed?
If the work is still exposed, the simplest path is normally to schedule the required County inspection before covering it. If the work has already been covered, concealed or completed, the next step depends on the permit, the inspection that was missed and the County’s direction.
Orange County’s Private Provider Manual specifically states that covered work must be exposed for inspection unless Orange County grants an exemption, and that affidavits, photographs and engineer letters are not automatically accepted in place of required inspections. An engineer letter may be useful when the County or Building Official specifically authorizes that approach.
Orange County Inspection FAQ
Where do I find which inspections my permit actually requires?
Use the inspection requirements and history associated with your specific permit in Orange County’s Fast Track system. The general code list is a reference; not every permit requires every inspection.
Can I cover work after I take photos?
Do not rely on photos as permission to cover required work. If an inspection is required, obtain the required approval before concealment unless Orange County gives project-specific direction otherwise.
Can a Florida PE write a letter for a missed framing, slab, rough-in or roof inspection?
A PE can evaluate and document appropriate engineering issues within the engineer’s scope, but whether Orange County accepts a letter in place of a missed County inspection is an AHJ decision. Confirm the requested remedy with the inspector or plan reviewer first.
What are the most common inspections that become difficult after the work is covered?
Foundations/footings, monolithic slabs, reinforcing steel, lintels/tie beams, framing, insulation, lath, roof in-progress work, underground electrical/plumbing, rough-in electrical/plumbing/mechanical and concrete-encased bonding are all much easier to verify before concealment.
Official Orange County resources
Orange County Division of Building Safety handles building, electrical, gas, mechanical, plumbing, refrigeration, roofing and solar inspections. Inspection scheduling and permit tracking are available through Fast Track. For inspection requests/results, Orange County lists 407-836-5550, option 1.
Source basis: Orange County inspection-type code chart and Orange County Building Safety / Private Provider guidance reviewed September 2026. Always verify the current permit record and County direction because inspection requirements and procedures can change.